Question: What is true when controlling the schedule during project execution and control? A) Schedule creep is acceptable if it results in useful new features at
What is true when controlling the schedule during project execution and control?
A) Schedule creep is acceptable if it results in useful new features at an acceptable cost.
B) Project managers use schedule variance analysis as the primary guide for deciding whether to recommend actions or changes to the schedule.
C) Small schedule slips are important and require immediate action.
D) If work cannot be brought back on schedule, changing the schedule is not an option.