Question: You have been asked to use the expected-value model to assess the risk in developing a new product. Each strategy requires a different sum of
You have been asked to use the expected-value model to assess the risk in developing a new product. Each strategy requires a different sum of money to be invested and produces a different profit payoff as shown below:
.png)
Assume that the probabilities for each state are 30 percent, 50 percent, and 20 percent, respectively.
a. Using the concept of expected value, what risk (i.e., strategy) should be taken?
b. If the project manager adopts a go-for-broke attitude, what strategy should be selected?
c. If the project manager is a pessimist and does not have the option of strategy S5, what risk would be taken?
d. Would your answer to part c change if strategy S5 were anoption?
States of Nature Strategy Complete Failure Partial Success Total Success St e30K> 70K 40K 50K 150K $50K 80K> 70K
Step by Step Solution
3.31 Rating (166 Votes )
There are 3 Steps involved in it
We can get these values by multiplying each of the possible outcomes by the likelihood ... View full answer