Question: What should the project manager do first when he decides to use the analogous estimating approach in his project? a. Confirm with team members the

What should the project manager do first when he decides to use the analogous estimating approach in his project?

a.

Confirm with team members the algorithm which will be used to calculate resource quantities

b.

Create an estimation for the team and physical resources at the activity level

c.

Research the organisational historical information

d.

Check the overall budget stated in the project charter and then estimate activity resources using the parametric technique