Question: What tool is commonly used to present a project's schedule that shows tasks, dates, and resources allocated? a. Windrose chart b. Sunburst chart c. Sankey

What tool is commonly used to present a project's schedule that shows tasks, dates, and resources allocated?

a. Windrose chart
b. Sunburst chart
c. Sankey chart
d. Gantt chart