Question: What would be the estimated project activity duration using a three-point estimation technique if the pessimistic value was 5 days, optimistic was 3 and the

What would be the estimated project activity duration using a three-point estimation technique if the pessimistic value was 5 days, optimistic was 3 and the most likely was 4 using the triangular distribution method?

4 days

5 days

3 days

None of the above