Question: What would be the estimated project activity duration using a three-point estimation technique if the pessimistic value was 5 days, optimistic was 3 and the
What would be the estimated project activity duration using a three-point estimation technique if the pessimistic value was 5 days, optimistic was 3 and the most likely was 4 using the triangular distribution method?
| 4 days | |
| 5 days | |
| 3 days | |
| None of the above |