Question: For an activity, the optimistic duration is 5 days, the most likely duration is 8 days, and the pessimistic duration is 1 2 days. What

For an activity, the optimistic duration is 5 days, the most likely duration is 8 days, and the pessimistic duration is 12 days. What is the estimated duration using the three-point estimation technique?Select one:A.9 daysB.8 daysC.7 daysD.10 days