Question: For an activity, the optimistic duration is 5 days, the most likely duration is 8 days, and the pessimistic duration is 1 2 days. What
For an activity, the optimistic duration is days, the most likely duration is days, and the pessimistic duration is days. What is the estimated duration using the threepoint estimation technique?Select one:A daysB daysC daysD days