Question: What would be the estimated time for completion if time estimates for GUI design are as follows: optimistic = 2 weeks; pessimistic = 4 weeks;

What would be the estimated time for completion if time estimates for GUI design are as follows: optimistic =2 weeks; pessimistic =4 weeks; realistic =3 weeks?
3 weeks
5 weeks
7 weeks
8 weeks
 What would be the estimated time for completion if time estimates

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!