Question: what would the CPM look like for the following: Task ID Task Name Description Start Date End Date Duration Dependencies Notes 1 Capacity Utilization in

what would the CPM look like for the following:

Task ID Task Name Description Start Date End Date Duration Dependencies Notes
1 Capacity Utilization in SAP Main project deliverables 4/1/2023 6/30/2023 3 months
1.1 Evaluate Current Process Review Current Process 4/24/2023 4/28/2023 4 days
1.1.1 Document Current Process Flow Chart Process 4/25/2023 4/26/2023 2 days
1.1.2 Analyze Process Flow Evaluate current process flow 4/27/2023 4/27/2023 0.5 days
1.1.3 Identify Bottle necks Where are bottlenecks observed 4/27/2023 4/27/2023 0.5 days
1.1.4 Document current Lead time factors What factors current lead time 4/25/2002 4/26/2023 1 day Can be done at same time as Flow charting.
1.2 Look at capacity tools inside of SAP Evaluate the capacity tools within SAP 1/3/1900 5/7/2023 6 days
1.2.1 Identify enhancements update configuration 5/6/2023 5/7/2023 1 day
1.3 Run Machine Time Studies Conduct time studies on machines 5/1/2023 5/15/2023 14 days 1.1
1.3.1 Cut to length Time Study Time study on Cut to length machines 5/1/2023 5/4/2023 3.5 days Time Studies can be done simultaneously.
1.3.2 Slitter Time Study Time study on Slitter machines 5/5/2023 5/8/2023 3.5 days
1.3.3 Roll Form Time Study Time Study on roll form machines 5/9/2023 5/12/2023 3.5 days
1.3.4 Analyze Time Study results How do time studies compare to current routing 5/12/2023 5/15/2023 3.5 days 1.3.1/2/3
1.4 Adjust routing Times where applicable Update routing times based on findings 5/15/2002 5/18/2023 3 days 1.3
1.4.1 Adjust Cut to Length routing Adjust times on Cut to Length machines to match Time Study 5/15/2023 5/16/2023 1 day adjustment to routing times can be done simultaneously
1.4.2 Adjust Slitter Routing Adjust times on Slitting machines to match Time Study 5/16/2023 5/17/2023 1 day
1.4.3 Adjust Roll Form Times Adjust Tables for Roll Form times where applicable 5/17/2023 5/18/2023 1 day
1.5 Recost Materials Recost materials where routing times have changed 5/19/2023 5/20/2023 1 day 1.4
1.6 Train on Capacity Tools Provide training on SAP capacity tools 5/21/2023 5/25/2023 4 days 1.2
1.6.1 Identify who will be trained Who needs trained 5/1/2023 5/3/2023 This can be done at start of project
1.6.2 Provide documentation How to use Tools 5/21/2023 5/25/2023 Provide documentation as perform training
1.6.3 Provide training Train on process 5/21/2023 5/25/2023
1.7 Reduce lead times down to six weeks Implement strategies to reduce lead times 6/1/2023 6/30/2023 30 days 1.5
1.7.1 Document steps to reduce lead times What will steps involve 5/25/2023 5/23/2023
1.8 Document future enhancements Any identified future projects 6/30/2023 7/1/2023 2 days 1.7
1.8.1 Reduce lead time down to 4 week How do we get to 4 weeks 7/1/2023 9/1/2023 60 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!