When a change order to the construction contract is required, the agency CM should: 


a) request a recovery schedule from the contractor 


b) request that the contractor update the Milestone Schedule


c) establish fixed scheduled completion dates for the impacted work 


d) request a schedule impact analysis and cost estimate from the contractor