Question: When a contractor performs work beyond that required by the contract without a formal change order and it is perceived that such work was ordered
When a contractor performs work beyond that required by the contract without a formal change order and it is perceived that such work was ordered by the Government or caused by Government fault, this is defined as? Bilateral modification O Constructive change O Protest O Unauthorized commitment
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
