Question: When a contractor performs work beyond that required by the contract without a formal change order and it is perceived that such work was ordered

When a contractor performs work beyond that required by the contract without a formal change order and it is perceived that such work was ordered by the Government or caused by Government fault, this is defined as? Bilateral modification O Constructive change O Protest O Unauthorized commitment