Question: When a new system will run in one business unit and will later be implemented in other units, what migration approach is being used? A.
-
When a new system will run in one business unit and will later be implemented in other units, what migration approach is being used?
A. direct
B. parallel
C. pilot
D. testing
-
A business school has developed a new HR system. It decides to switch from the old to the new one on Saturday March 12th. What type of migration approach is the school using?
A. direct
B. parallel
C. pilot
D. testing
-
The build phase of the systems development life cycle (SDLC) consists of which of the following sub-processes:
installation, operations, maintenance
investigation, feasibility analysis, system analysis
system design, programming, testing
system design, implementation, maintenance
-
During the definition phase of the systems development life cycle (SDLC), the firm will perform three types of feasibility analysis. Which of the following is NOT one of them?
A. technical feasibility
B. operational feasibility
C. economic feasibility
D. practical feasibility