Question: When a project manager must reduce project duration but resources are constrained, creating a software program that will have less functionality than originally planned or
When a project manager must reduce project duration but resources are constrained, creating a software program that will have less functionality than originally planned or building a house without the bonus room and the basement that the owner originally specified in the plans would both be examples of Page 3: 3 fast-tracking. use critical-chain project management. reduce project scope. Page 4: 4 compromise quality. do it twice-fast and correctly