Question: When a project manager must reduce project duration but resources are constrained, creating a software program that will have less functionality than originally planned or
When a project manager must reduce project duration but resources are constrained, creating a software program that will have less functionality than originally planned or building a house without the bonus room and the basement that the owner originally specified in the plans would both be examples of
A compromise quality.
B
reduce project scope.
C
use criticalchain project management.
D do it twicefast and correctly.
E fasttracking.