Question: When an activity on a PERT network has these time estimates: optimistic = 1 , most likely = 3 , and pessimistic = 5 ,

When an activity on a PERT network has these time estimates: optimistic =1, most likely =3, and pessimistic =5, the expected activity time is 3.