Question: When an activity on a PERT network has these time estimates: optimistic = 1 , most likely = 3 , and pessimistic = 5 ,
When an activity on a PERT network has these time estimates: optimistic most likely and pessimistic the expected activity time is
Group of answer choices
True
False
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
