Question: When an earned value analysis is done, a positive schedule variance indicates that the contractor is ahead of schedule in terms of the value of

When an earned value analysis is done, a positive schedule variance indicates that the contractor is ahead of schedule in terms of the value of work accomplished.
Question 5 options:
True
False