Question: When analyzing quality for a project a Project Manager decides to use a tool that provides a creative way to review the causes or potential

When analyzing quality for a project a Project Manager decides to use a tool that provides a creative way to review the causes or potential causes of a problem. Which tool is this?
When analyzing quality for a project a Project Manager decides to use a tool that provides a creative way to review the causes or potential causes of a problem. Which tool is this?
Cause and effect diagram
Statistical sampling
Pareto diagram
Control chart