Question: When are Bottom - Up methods of estimating are mainly used? a . For very small projects.b . At the beginning of a project.c .

When are Bottom-Up methods of estimating are mainly used? a.For very small projects.b.At the beginning of a project.c.After the Work Breakdown Structure (WBS) has been completed.d.When only rough estimates are required.