Question: When are Bottom - Up methods of estimating are mainly used? a . For very small projects.b . At the beginning of a project.c .
When are BottomUp methods of estimating are mainly used? aFor very small projects.bAt the beginning of a project.cAfter the Work Breakdown Structure WBS has been completed.dWhen only rough estimates are required.