Question: When building a project schedule, what is a precedence for a given task? Group of answer choices Duration of task None of these listed Task
When building a project schedule, what is a precedence for a given task?
Group of answer choices
Duration of task
None of these listed
Task owner
Start date of task
Task that must be completed first