Question: When calculating a waste factor for concrete you would use the same value(%) for placement using the direct chute method as placement using the direct
When calculating a waste factor for concrete you would use the same value(%) for placement using the direct chute method as placement using the direct chute method as placement that requires the use of a concrete pump. True or false