Question: When calculating your Materials Requirements Plan (MRP), you have a net requirement of 122 in week 4. Your order policies are Q=50 and LT=3. Therefore
When calculating your Materials Requirements Plan (MRP), you have a net requirement of 122 in week 4. Your order policies are Q=50 and LT=3. Therefore your planned order release will be 150 units in week 1, and your ending inventory in week 4 will be 0.
True/False