Question: When carrying out a distribution process, a logistics manager provides you with the table below explaining the precedence relationships between eight different operations as well
When carrying out a distribution process, a logistics manager provides you with the table below
explaining the precedence relationships between eight different operations as well as their
completion times
What is the minimum duration of this mission
Determine the operations that must be monitored with maximum attention
It is to highlight that each delay in these activities will negatively impact the final duration
Xi
activity
PXi Duration
A F
B D C
C G
D E G
E H
F H
G H
H