Question: When changes are agreed upon, a new _ _ _ _ should be established and used as the benchmark against which actual project performance will

When changes are agreed upon, a new ____ should be established and used as the benchmark against which actual project performance will be compared.
Group of answer choices
baseline plan
management matrix
work expectations form
time-cost diagram