Question: When crashing your project you added one developer and one quality assurance tester to non - critical path tasks. What is the outcome of this

When crashing your project you added one developer and one quality assurance tester to non-critical path tasks. What is the outcome of this project scheduling change?
Decrease in project cost
Increase in project scope
No effect
Deliver your project early