Question: When deciding the time to allow for a bid response, the procurement function within a buying organization should do each of the following except: a
When deciding the time to allow for a bid response, the procurement function within a buying organization should do each of the following except:
a consider the complexity of the bid
b pay attention to the time of the year and its potential impact on the suppliers ability to respond
c coordinate with internal customers to identify a response time that would be acceptable to them
d prefer a short window to reduce opportunities for negotiation
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock