Question: When deciding the time to allow a bid response, the supply professional should do each of the following, EXCEPT: A. Consider the complexity of the

When deciding the time to allow a bid response, the supply professional should do each of the following, EXCEPT:

A. Consider the complexity of the bid

B. Use a short response time to limit supplier participation

C. Pay attention to the time of the year and its potential on suppliers ability to respond

D. Work with internal customers to select a response time acceptable to all affected parties