Question: When designing an overflow - type spillway with a design flood rate of 8 0 0 m 3 / s , when the elevation of

When designing an overflow-type spillway with a design flood rate of 800 m3/s, when the elevation of the apex of the spillway is 108 m and the planned flood level is 112 m,
(1) Find the width of the spillway,
(2) Find the road surface curve using the WES method. Assume that the slopes of the upstream and downstream sides of the spillway are vertical:horizontal of 3:2 and 2:1, respectively, and the flow coefficient is 2.0. And ignore the access head to spillway.
(3) Determine the point where the downstream slope (2:1) begins.