Question: When developing a definitive estimate using R . S . Means, the unit prices from this standard can be adjusted by which of the following

When developing a definitive estimate using R.S. Means, the unit prices from this standard can be adjusted by which of the following cost factors, if project-specific information is known to differ from the basis used in R.S. Means standard that is being used?
A. Location, Time (Escalation)
B. Location, Time (Escalation), Productivity
C. Location, Productivity, Different Crew Mix
D. Location, Time (Escalation), Productivity, Labor Wage Rate, Different Crew Mix