Question: When developing probabilistic estimates of project duration, it is necessary to know which of the follow? The mean and variance of every activity The mean

When developing probabilistic estimates of project duration, it is necessary to know which of the follow?
The mean and variance of every activity
The mean and variance of every activity on the critical path
The standard deviation of activities on the critical path.
The distribution of activity time.
 When developing probabilistic estimates of project duration, it is necessary to