Question: When developing probabilistic estimates of project duration, it is necessary to know which of the following? Multiple Choice the mean and variance of every activity

When developing probabilistic estimates of project duration, it is necessary to know which of the following?
Multiple Choice
the mean and variance of every activity
the mean and variance of activities on the critical path
the standard deviation of activities on the critical path
each activity's probability of completion
the distribution of activity times

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!