Question: When MRP calculates the future needs for components and raw materials to create a backward schedule, MRP is: Exploding the Bihof Material Sourcing the Bill

When MRP calculates the future needs for components and raw materials to create a backward schedule, MRP is:
Exploding the Bihof Material
Sourcing the Bill of Material
Fulfilling the Bill of Material
 When MRP calculates the future needs for components and raw materials