Question: When MRP calculates the future needs for components and raw materials to create a backward schedule, MRP is A. Eliminating the Bill of Material B.

When MRP calculates the future needs for components and raw materials to create a backward schedule, MRP is

A.

Eliminating the Bill of Material

B.

Sourcing the Bill of Material

C.

Factoring the Bill of Material

D.

Exploding the Bill of Material

E.

Fulfilling the Bill of Material