Question: When project costs begin to increase tasks generally exceed the planned schedule duration. There are four factors that contribute to this effect. Which of the

When project costs begin to increase tasks generally exceed the planned schedule duration. There are four factors that contribute to this effect. Which of the following is not one of those factors? Group of answer choices a. Cost of funds allocated during planning b. Deterioration of the work product over time c. Relearning as a result of repeated work stoppage and restart d. Underrunning the baseline budget