Question: MC Qu . 1 9 ( Static ) When reducing project duration, the crash...When reducing project duration, the crash cost per unit has to be

MC Qu.19(Static) When reducing project duration, the crash...When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known. After this, the critical path must be identified. What is the next step?Multiple Choice: Calculate the optimum cost-time point; Find the activity with the lowest crash cost; Calculate indirect cost per time unit; Find the activity with the steepest cost slope; Calculate the crash point.