Question: MC Qu . 1 9 ( Static ) When reducing project duration, the crash...When reducing project duration, the crash cost per unit has to be
MC QuStatic When reducing project duration, the crash...When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known. After this, the critical path must be identified. What is the next step?Multiple Choice: Calculate the optimum costtime point; Find the activity with the lowest crash cost; Calculate indirect cost per time unit; Find the activity with the steepest cost slope; Calculate the crash point.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
