Question: When reducing project duration, the duration for a project that is optimal is at the point where q , Direct costs are the lowest The
When reducing project duration, the duration for a project that is optimal is at the point where
Direct costs are the lowest
The project changes from timeconstrained to resourceconstrained
Total project costs are the lowest
Direct costs equal indirect costs
Indirect costs are the lowest