Question: When reducing project duration, the duration for a project that is optimal is at the point where q , Direct costs are the lowest The

When reducing project duration, the duration for a project that is optimal is at the point where q,
Direct costs are the lowest
The project changes from time-constrained to resource-constrained
Total project costs are the lowest
Direct costs equal indirect costs
Indirect costs are the lowest
 When reducing project duration, the duration for a project that is