Question: When reducing project duration, the duration for a project that is optimal is at the point where Select one: a. total project costs are the
When reducing project duration, the duration for a project that is optimal is at the point where Select one: a. total project costs are the lowest. b. the project changes from time-constrained to resource-constrained. c. indirect costs are the lowest. d. direct costs are the lowest. e. direct costs equal indirect costs