Question: When reducing the planned duration of a project using the time - cost CPM model, start with the normal schedule, find the critical path, and
When reducing the planned duration of a project using the timecost CPM model, start with the normal schedule, find the critical path, and reduce the path time by one day using the
highestcost activity
lowestcost activity
two activities requiring the lowest use of overhead
two activities requiring the highest use of overhead
most automated activity