Question: When resources are not the constrained in a project, which of the following statement is NOT TO BE CONSIDERED for reducing project duration? A .

When resources are not the constrained in a project, which of the following statement is NOT TO BE CONSIDERED for reducing project duration?
A. Adding resources
B. Reduce project scope
C. Outsourcing project
Scheduling overtime
Do it twice - fast and correctly