Question: When scheduling a project, you can assign a task to a role at any point, but you can't assign a task to a person until

When scheduling a project, you can assign a task to a role at any point, but you can't assign a task to a person until you know which of the following? O How long the task will take O If the task has a fixed duration If there are discretionary dependencies O The work packet deadline