Question: When should the bidder submit the payment bond, the performance bond, and the certificate of insurance? during the bid phase after Agreement, but before the

When should the bidder submit the payment bond, the performance bond, and the certificate of insurance?
during the bid phase
after Agreement, but before the Notice to Proceed
prior to advertising for bids
after bid opening, but before Award of Contract
after Notice to Proceed
after award, but before owner signs the Agreement