Question: When solving a project using Project Management, the Critical Path Method (aka CPM), and Activity on Nodes, the slack on activities on the critical path
When solving a project using Project Management, the Critical Path Method (aka CPM), and Activity on Nodes, the slack on activities on the critical path will always be equal to:
| 0 | ||
| 1 | ||
| 2 | ||
| 3 | ||
| 4 | ||
| Impossible to determine with the information given |