Question: When the contracting officer needs time to determine if the contents of the tanks are considered hazardous material, and the contracting officer stops the contractor's
When the contracting officer needs time to determine if the contents of the tanks are considered hazardous material, and the contracting officer stops the contractor's work, under what authority could the contracting officer grant a time extension for this delay incurred? FAR 52.249-10 Default Clause FAR 52.242-15, Stop Work Order FAR 52.236-13 Accident Prevention FAR 52.242-14, Suspension of Work Clause