Question: When the resource levelling feature is activated, how does Project automatically resolve resource overallocations? options: Custom options regarding resource levelling are entered by the user.
When the resource levelling feature is activated, how does Project automatically resolve resource overallocations?
options:
|
| Custom options regarding resource levelling are entered by the user. |
|
| Project increases the costs associated with the overallocated resources and the schedule remains unchanged. |
|
| Project delays or splits resource work, thus delaying start times. The project finish date may or may not pushed back. |
|
| Project delays or splits resource work, thus delaying start times. The project finish date is pushed back. |