Question: When the resource levelling feature is activated, how does Project automatically resolve resource overallocations? Custom options regarding resource levelling are entered by the user.
When the resource levelling feature is activated, how does Project automatically resolve resource overallocations? Custom options regarding resource levelling are entered by the user. Project delays or splits resource work, thus delaying start times. The project finish date may or may not pushed back. Project increases the costs associated with the overallocated resources and the schedule remains unchanged. Project delays or splits resource work, thus delaying start times. The project finish date is pushed back.
Step by Step Solution
There are 3 Steps involved in it
The detailed answer for the above question is provided below When the resource leveling feature is a... View full answer