Question: When translated into a project network, a work package will become Multiple Choice a critical path. a single activity. a milestone. an arrow. one or

When translated into a project network, a work package will become
Multiple Choice
a critical path.
a single activity.
a milestone.
an arrow.
one or more activities.
 When translated into a project network, a work package will become