Question: When using a network diagram to manage a project, a critical activity is when Group of answer choices the earliest start time is flexible the

When using a network diagram to manage a project, a critical activity is when
Group of answer choices
the earliest start time is flexible
the latest start time is flexible
the latest start time is 10% later than the earliest start time
the earliest start time and the latest start time are equal