Question: Reliance soaps Ltd is developing a new packaging for its detergent. This project consists of nine activities, A to I. Activity Completion time (weeks) A

Reliance soaps Ltd is developing a new packaging for its detergent. This project consists of nine activities, A to I.

Activity Completion time (weeks) A 6 B 9 C 8 D 5 E 10 F 6 G 14 H 11 I 9

The immediate precedence relationships are: Activity B must be finished before D and E can start. Activity C must be finished before A and D can start. Activity E must be finished before G and H can start. Activity F must be finished before C and I can start.

(i) Draw an appropriate network diagram to correctly represent the project. (ii) Calculate the Earliest start time, the Earliest finishing time, the Latest start time, the Latest finishing and the Float for each activity.

(iii) Identify the critical path and calculate the overall project completion time. (iv) Explain clearly (with reasons) the effect upon the overall project completion time if the completion time for activity B increases from 9 weeks to 17 weeks while at the same time the completion time for activity I increases from 9 weeks to 16 weeks. Identify what action, if any, which the project manager has to take.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!