Question: When using SAP's consumption based planning: MRP will run and create a requisition when the stock quantity is below the reorder point quantity, SAP will
When using SAP's consumption based planning: MRP will run and create a requisition when the stock quantity is below the reorder point quantity, SAP will set the requisition release date to the current date... How will the requisition delivery date be calculated?
Group of answer choices
Uses todays date
Release date plus planned delivery time
Release date plus GR processing time
Release date plus both planned delivery time and GR processing time
Planned date minus planned delivery time