Question: When using SAP's consumption based planning: MRP will run and create a requisition when the stock quantity is below the reorder point quantity, SAP will

When using SAP's consumption based planning: MRP will run and create a requisition when the stock quantity is below the reorder point quantity, SAP will set the requisition release date to the current date... How will the requisition delivery date be calculated?

Group of answer choices

Uses todays date

Release date plus planned delivery time

Release date plus GR processing time

Release date plus both planned delivery time and GR processing time

Planned date minus planned delivery time