Question: When work has been scheduled in a shop that does not have sufficient resources to complete the schedule on time, the system that generated the

When work has been scheduled in a shop that does not have sufficient resources to complete the schedule on time, the system that generated the schedule is called which of the following?

a. infinite loading

b. Machine limited

c. finite loading

d. labor limited

e. Constrained