Question: When would you choose to split a task? when no other resources are available who are qualified to perform both tasks when both tasks are
- When would you choose to split a task?
- when no other resources are available who are qualified to perform both tasks
- when both tasks are short
- when both tasks are long
- when one task duration is short and the other is long
- An ellipsis () in a filter name indicates that _____.
- the filter accepts a wildcard in the test value
- the filter is a custom filter
- the filter is already applied
- the filter prompts for a value to filter by
- Each timeline bar in a timeline view can have its own _____.
- tasks
- date range
- bars and callouts
- date range, bars, and callouts
- Which method is the least effective way to ensure that the entire header text is visible in a table column?
- turn on the Header Text Wrapping checkbox
- change the value in the Width box
- drag the vertical divider to the right to widen the column
- click the Best Fit button
- The _____ view, which has an icon on the _____ tab, helps you see individual assignments in a table and time-phased grid.
- Resource Usage; View
- Task Usage; Task
- Gantt Chart; View
- Task Usage; View
- For which task would you want to turn effort-driven scheduling off?
- a delivery milestone
- obtaining requirements
- a team meeting
- testing code
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock