Question: Where does a project manager get the knowledge to create a WBS? Question 16 options: A) Project charter B) Previous similar projects C) Project team
Where does a project manager get the knowledge to create a WBS?
Question 16 options:
|
|
|
| A) | Project charter |
|
|
|
| B) | Previous similar projects |
|
|
|
| C) | Project team |
|
|
|
| D) | All answers are correct. |
The critical path is
Question 17 options:
|
|
|
| A) | The path of tasks on a network diagram representing the minimum total duration for the project. |
|
|
|
| B) | The tasks with zero or negative float. |
|
|
|
| C) | The path of tasks on a network diagram with the longest total duration. |
|
|
|
| D) | All answers are correct. |