Question: Where does a project manager get the knowledge to create a WBS? Question 16 options: A) Project charter B) Previous similar projects C) Project team

Where does a project manager get the knowledge to create a WBS?

Question 16 options:

A)

Project charter

B)

Previous similar projects

C)

Project team

D)

All answers are correct.

The critical path is

Question 17 options:

A)

The path of tasks on a network diagram representing the minimum total duration for the project.

B)

The tasks with zero or negative float.

C)

The path of tasks on a network diagram with the longest total duration.

D)

All answers are correct.